Public Information Meeting

Project ID: 5709-00-01/70

Town of Excelsior, North Reedsburg Road

Northwoods Drive to STH 23

Sauk County, Wisconsin

The Town of Excelsior will host a public involvement meeting for the above project on North Reedsburg Road on:

Wednesday, May 15, 2024, from 6:30PM to 7:30PM,

at the Town of Excelsior – Town Hall, 100 E Broadway Street, Rock Springs, WI 53961.

A brief presentation on the project is scheduled to begin at 6:30PM. The remainder of the meeting will follow an open house format. Adjacent property owners are encouraged to attend the meeting.

The purpose of this meeting is to obtain public feedback on the proposed project. 

The objective of the project is to rectify pavement shortcomings and enhance the sight distance along North Reedsburg Road from Northwoods Drive to STH 23. The modifications aim to enhance the safety of the roadway corridor as a whole.

The project will encompass two different approaches for improving the roadway, each applied to specific sections of the roadway.  

Concept one involves reconditioning the existing roadway by pulverizing the current asphalt in place and overlaying it with new 2.5-inch HMA pavement. This method will be employed in areas where the roadway currently meets the 45-mph design speed.

Concept two entails a complete reconstruction of the roadway and will be implemented in three project sections that presently do not meet the 45-mph design speed. These sections feature sag and crest vertical curves requiring enhancements to improve the roadway sight distance. The improvements will include subgrade enhancements with new base aggregate and new 2.5-inch HMA pavement.

In both improvement concepts the roadway will be paved with 11-foot lanes and 2-foot aggregate shoulders vs the existing roadway that currently has 10-foot lanes and 1-2 foot aggregate shoulders. 

The project is currently scheduled for 2027 construction. During construction, North Reedsburg Road will be closed to through traffic.  No detour will be signed.  Access to local traffic and businesses will be allowed.  There may be times during construction that traffic local traffic may be delayed for the roadway grading and culvert work required for the project.